For new construction, IPMVP Option D builds a 'virtual baseline' via thermal simulation of a reference building (typically meeting current RT/RE requirements but with standard, non-performant equipment) and then compares it to the actual delivered building.
True
Option D for new construction uses a virtual baseline: a model of an equivalent building built to the minimum regulatory performance (RT2012 or RE2020 with standard equipment). The reporting side is the delivered building, with its model calibrated against real measurements. Savings are the difference between the virtual baseline and the reporting model. Typical use cases include HQE/BREEAM projects and labels that require proof of performance versus a code-compliant scenario.
Get the virtual baseline assumptions blessed by the owner before construction — retro-fitting them after handover invariably triggers disputes.
CMVP bank in preparation
The full CMVP bank isn't available yet. Drop your email to get notified at launch and grab an early-bird discount.
Join the waitlist →See the 9 other CMVP practice questions
Related questions
- Which IPMVP option uses field measurement of the key parameter(s) explaining the savings ONLY (with the others estimated) for an isolable ECM?2. IPMVP Options · Option A vs B
- IPMVP Option C (Whole Facility) is recommended when the expected savings represent more than 10 % of the total building consumption and several ECMs coexist (making individual A/B isolation impractical).2. IPMVP Options · Anwendungsfall Option C
- IPMVP Option D uses a calibrated thermal simulation model (eQUEST, EnergyPlus, IES-VE or equivalent) when baseline or reporting data are unavailable or unreliable, for example in new construction or full system replacements.2. IPMVP Options · Option D Kalibrierte Simulation
- In IPMVP, routine adjustments correct regular variations (weather, occupancy, production) via regression or factor, while non-routine adjustments (NRA) handle unplanned static changes (added floor area, extra shift, refurbishment) that occur between baseline and reporting periods.3. Periods & adjustments · Routine vs. Non-Routine Adjustments
- An IPMVP-compliant M&V Plan typically covers 13 key sections: ECM description, chosen option, measurement boundary, baseline and reporting periods, adjustment variables, analysis procedure, energy prices, metering, QA/QC, target uncertainty level, budget and reporting format.5. M&V Plan · Pflichtabschnitte