IPMVP Option C (Whole Facility) is recommended when the expected savings represent more than 10 % of the total building consumption and several ECMs coexist (making individual A/B isolation impractical).
True
Option C is holistic, captures ECM interactions and is simple to deploy because it relies on the main utility meter. The downsides are lower precision (consumption noise), and the need for sophisticated routine adjustments for weather, occupancy and production. A typical use case is a whole-building energy audit on a tertiary site with five or more concurrent renovations where isolation is not cost-effective.
Below the 10 % rule of thumb, savings get lost in measurement noise — use A or B isolation instead.
CMVP bank in preparation
The full CMVP bank isn't available yet. Drop your email to get notified at launch and grab an early-bird discount.
Join the waitlist →See the 9 other CMVP practice questions
Related questions
- Which IPMVP option uses field measurement of the key parameter(s) explaining the savings ONLY (with the others estimated) for an isolable ECM?2. IPMVP Options · Option A vs B
- IPMVP Option D uses a calibrated thermal simulation model (eQUEST, EnergyPlus, IES-VE or equivalent) when baseline or reporting data are unavailable or unreliable, for example in new construction or full system replacements.2. IPMVP Options · Option D Kalibrierte Simulation
- For new construction, IPMVP Option D builds a 'virtual baseline' via thermal simulation of a reference building (typically meeting current RT/RE requirements but with standard, non-performant equipment) and then compares it to the actual delivered building.2. IPMVP Options · Option D für Neubau
- In IPMVP, routine adjustments correct regular variations (weather, occupancy, production) via regression or factor, while non-routine adjustments (NRA) handle unplanned static changes (added floor area, extra shift, refurbishment) that occur between baseline and reporting periods.3. Periods & adjustments · Routine vs. Non-Routine Adjustments
- An IPMVP-compliant M&V Plan typically covers 13 key sections: ECM description, chosen option, measurement boundary, baseline and reporting periods, adjustment variables, analysis procedure, energy prices, metering, QA/QC, target uncertainty level, budget and reporting format.5. M&V Plan · Pflichtabschnitte