In the sequence for checking a KNX installation, which check is carried out immediately after checking the polarity of all bus devices?

KNX BasicLearnKNX InstallationMedium
Answer

C — Measuring the bus voltage at each bus cable end

Correct: The polarity check is followed by measuring the bus voltage (minimum 21 V) at each bus cable end.

Source

KNX Basic Course Documentation — 17 — p. 118

All proposed choices (exam context)
  1. A.Measuring the insulation resistance of the bus cables
  2. B.The visual check of the bus cable-end marking
  3. C.Measuring the bus voltage at each bus cable end
  4. D.Recording the test results
Full bank

Keep going with the full KNX Basic bank

Keep going with the full KNX Basic bank: unlimited timed mock exams, detailed answers, history. From €9 (one-time payment).

See pricing — from €9
Want more?

See the 9 other KNX Basic practice questions

Related questions

Question from our independent practice bank. KNX Basic is a registered trademark of KNX Association, not affiliated with CertifBus.

Last updated: 19 May 2026

See pricing — from €9
KNX Basic pack · from €9
KNX BASIC & ADVANCED

Ready to find out where you really stand?

10 free questions every day, no account needed. Full access only if you decide to go all the way.

+1/−0,5 official scoringFR·EN·DE interface and explanations9 from · one-time payment
Newsletter

Get launch announcements

We'll email you when new KNX questions, a guide or a tool is published. No spam.

Unsubscribe in 1 click. No sharing with third parties.