Question
In the sequence for checking a KNX installation, which check is carried out immediately after checking the polarity of all bus devices?
Answer
C — Measuring the bus voltage at each bus cable end
Correct: The polarity check is followed by measuring the bus voltage (minimum 21 V) at each bus cable end.
Source
KNX Basic Course Documentation — 17 — p. 118
All proposed choices (exam context)
- A.Measuring the insulation resistance of the bus cables
- B.The visual check of the bus cable-end marking
- C.Measuring the bus voltage at each bus cable end✓
- D.Recording the test results
Full bank
Keep going with the full KNX Basic bank
Keep going with the full KNX Basic bank: unlimited timed mock exams, detailed answers, history. From €9 (one-time payment).
See pricing — from €9 →Want more?
See the 9 other KNX Basic practice questions
Related questions
- ETS is available in four versions. Which statement is correct?1. KNX System Arguments · advantages-and-ets
- ETS Lite is limited to projects with how many products, and is primarily intended for whom?1. KNX System Arguments · advantages-and-ets
- What does the "backward compatibility" of KNX mean in practice?1. KNX System Arguments · advantages-and-ets
- In which year was the KNX Association established, and what was it initially called?1. KNX System Arguments · history-and-standardization
- In 1999 the EIBA merged with two other European associations. Which ones?1. KNX System Arguments · history-and-standardization