Question
When does an S-mode KNX installation become ready for operation?
Answer
C — After the sensors and actuators have been downloaded with their application program via ETS.
Correct: the source states an S-mode installation is not ready until sensors and actuators are downloaded with the application program via ETS.
Source
KNX Basic Course Documentation — 3.3.1 — p. 37
All proposed choices (exam context)
- A.As soon as the devices are mechanically mounted and the bus voltage is present.
- B.Immediately, because S-mode application programs are pre-installed at the factory.
- C.After the sensors and actuators have been downloaded with their application program via ETS.✓
- D.Once individual addresses are assigned, even if no application program is loaded yet.
Full bank
Keep going with the full KNX Basic bank
Keep going with the full KNX Basic bank: unlimited timed mock exams, detailed answers, history. From €9 (one-time payment).
See pricing — from €9 →Want more?
See the 9 other KNX Basic practice questions
Related questions
- ETS is available in four versions. Which statement is correct?1. KNX System Arguments · advantages-and-ets
- ETS Lite is limited to projects with how many products, and is primarily intended for whom?1. KNX System Arguments · advantages-and-ets
- What does the "backward compatibility" of KNX mean in practice?1. KNX System Arguments · advantages-and-ets
- In which year was the KNX Association established, and what was it initially called?1. KNX System Arguments · history-and-standardization
- In 1999 the EIBA merged with two other European associations. Which ones?1. KNX System Arguments · history-and-standardization