Question

The baseline period in M&V must be representative of typical operating conditions before the ECM, capturing energy plus explanatory variables (weather, occupancy, production), and typically covers a full 12-month cycle for buildings.

CMVPLearnPeriods & adjustmentsMedium
Answer

True

A valid baseline period must span a complete seasonal cycle (12 months for HVAC-driven facilities) and reflect typical operations (not a period of partial refurbishment). It must capture energy, degree-days, occupancy and production where applicable, with conditions exhaustively documented. A weak baseline produces indefensible savings and is the single most common cause of disputes in audits or litigation.

Preparation tip

If the baseline year was atypical (COVID, plant shutdown), flag it early and seek owner approval before locking the M&V Plan.

Waitlist

CMVP bank in preparation

The full CMVP bank isn't available yet. Drop your email to get notified at launch and grab an early-bird discount.

Join the waitlist
Want more?

See the 9 other CMVP practice questions

Related questions

Question from our independent practice bank. CMVP is a registered trademark of Efficiency Valuation Organization, not affiliated with CertifBus.

Last updated: 19 May 2026

Join the waitlist
CMVP waitlist
KNX BASIC & ADVANCED

Ready to find out where you really stand?

10 free questions every day, no account needed. Full access only if you decide to go all the way.

+1/−0,5 official scoringFR·EN·DE interface and explanations9 from · one-time payment
Newsletter

Get launch announcements

We'll email you when a new bank ships (BACnet, Modbus, etc.) or a new tool. Plus an early-bird discount on first purchases. No spam.

Unsubscribe in 1 click. No sharing with third parties.